The following is an update submitted by Lennox and Addington County on the transportation and municipal servicing class environmental assessment:
PROJECT UPDATE
The County of Lennox and Addington (County) and Town of Greater Napanee (Town) are in the process of completing a Schedule C Municipal Class Environmental Assessment (MCEA). This MCEA will confirm proposed road improvements identified in the County’s Transportation Master Plan (TMP) to accommodate future traffic and anticipated developments within the Study Area and alleviate expected congestion on County Road 41 (Centre Street North).
Currently, the County and Town are preparing an Environmental Study Report (ESR) to identify the optimal location for additional road connections, including information such as:
- The project’s need and opportunities
- Existing conditions of the Study Area
- Possible alternative solutions and designs (road alignments) that can accomplish the project’s multiple criteria, along with a preferred solution
- Municipal servicing needs for anticipated new developments in the Study Area (e.g., water and sewer)
- The project’s anticipated environmental impacts and proposed mitigation measures to reduce or eliminate impacts
RECOMMENDED SOLUTION
The recommended solution features three new arterial roadways (see image below) with associated roundabout intersections and multi-use pathways for active transportation users:
- Roadway ‘E1’, which will run east-west and link County Road 1 West to County Road 41/Industrial Boulevard and Alkenbrack Street
- Roadway ‘S2’, which will run east-west and link a new north-south arterial roadway (‘W1’) to Belleville Road/Enviro Park Lane
- Roadway ‘W1’, which will run north-south and connect Bridge Street West/Cherrywood Parkway to Belleville Road/Jim Kimmett Boulevard
A solution to expand the water servicing network through potential connection points at Belleville Road, Richmond Park Drive, Kanvers Way and Beverly Street, as well as enhancements made to wastewater servicing through a Slash Road connection are also provided within the ESR.
MUNICIPAL CLASS EA PROCESS
Completing and publishing an ESR for review agencies and the public will satisfy Phase 4 of the Transportation and Utilities Class EA requirements, while the County’s updated TMP satisfied Class EA Phase 1 (Identify the Problem/Opportunity) and Class EA Phase 2 (Identify Alternative Solutions and Establish the Preferred Solution). Class EA Phase 3 (Examine Alternative Methods of Implementing the Preferred Solution) was completed as part of development of the ESR. The County and Town will proceed to Class EA Phase 5 (Implementation) after receiving and addressing comments stemming from the ESR’s public comment period.
WANT TO GET INVOLVED?
Consultation is an important part of the MCEA process, and we want to hear from you. The second of two planned Public Information Centres for the project is being held online through the County of Lennox and Addington’s website (https://lennox-addington.on.ca/public-notices). Visit the County’s website between October 23 and November 10, 2023 to learn more about the project and provide your questions and comments.
On behalf of the County and Town, please contact the project team at NapaneeRoadServicingEA@ghd.com if you would like to provide comments, request additional information, and/or be added to our project mailing list:
Chris Wagar
Director, Infrastructure Services
County of Lennox and Addington
T: 613-354-4883 Ext 3230
Jeff Cuthill
Director, Capital Works
Town of Greater Napanee
T: 613-856-2247
Vanessa Skelton, P. Eng.
Project Manager
GHD
T: 613-288-1727